|
Environmental Citizen Suit Brief Bank
PLAINTIFF'S MEMORANDUM OF LAW
IN SUPPORT OF MOTION FOR PRELIMINARY INJUNCTION
PRELIMINARY STATEMENT
Plaintiff, Hudson Riverkeeper Fund, Inc. ("Riverkeeper"),
submits this Memorandum of Law in Support of its Motion for an
Order pursuant to Rule 65(a) of the Federal Rules of Civil
Procedure enjoining the Yorktown Heights Sewer District; Town of
Yorktown; Aaron Bock, Town Supervisor; Allen Chadwick, Assistant
Town Supervisor; and Daniel Ciarcia, Town Engineer
("Defendants") from allowing any new sewer connections
to the Yorktown Heights Wastewater Treatment Plant ("Sewage
Plant") until the Sewage Plant complies with its permit. As
described in the accompanying affidavits, the Defendants' illegal
discharges of improperly treated sewage cause Plaintiff
irreparable harm.
ARGUMENT
I. A PRELIMINARY INJUNCTION SHOULD BE ISSUED TO PREVENT
DEFENDANTS FROM TAKING IN ANY MORE SEWAGE WHEN IT CAN NOT BE
PROPERLY TREATED.
In the Second Circuit, in order to obtain preliminary
injunctive relief, the moving party:
must demonstrate (1) that it will suffer irreparable
harm if the preliminary injunction is not issued, and (2)
that it is likely to succeed on the merits of its claims
or, in the alternative, has demonstrated sufficiently
serious questions regarding the merits of the claims and
the balance of hardships tips decidedly in its favor.
L. J.G. Stickley, Inc. v. Canal Dover Furniture Co., Inc.,
79 F.3d 258, 261-62 (2d Cir. 1996) (citing Tough
Traveler, Ltd. v. Outbound Products, 60 F.3d 964, 967 (2d
Cir. 1995)). The trial court may also consider likely
consequences to the parties and the overall public interest. See
Standard and Poor's Corp., Inc. v. Commodity Exch., Inc.,
683 F.2d 704, 711 (2d Cir. 1982). As explained below, Plaintiff
and the public interest will be irreparably harmed if a
preliminary injunction is not granted. Moreover, Plaintiff has a
strong likelihood of success on the merits.
A. Plaintiff And The Public Interest Will Suffer Irreparable
Harm If The Defendants Add Any New Sewer Connections To
Defendants' Overloaded Sewage Treatment Plant.
Plaintiff and its members are irreparably harmed by Defendants'
permit violations in two ways. First, Defendants' discharges are
destroying the recreational fishery of the Muscoot River, the
Muscoot Reservoir and the New Croton Reservoir. Second,
Defendants' discharges create serious health risks to consumers of
reservoir water.
1. Destruction of Fishery.
Plaintiff's members who fish or have fished in the Muscoot
River and the New Croton Reservoir are irreparably harmed by
Defendants' violations. Since January of 1991, the Defendants' own
Wastewater Facility Operation Reports ("WFORs") record
2,258 violations of the chlorine effluent limitation contained in
the Sewage Plant's State Pollutant Discharge Elimination System
permit No. NY-0026743 ("SPDES Permit"). Affidavit of
Stephanie L. Burns, sworn to on October 14, 1996 ("Burns Aff.")
¶¶ 11, 17, 22, Exs. A (SPDES Permit), F, K-M. Chlorine is
extremely toxic to fish and the organisms on which they depend.
Affidavit of Dr. Bruce A. Bell, sworn to on October 11, 1996
("Bell Aff.") ¶ 23.
The Hallocks Mill Brook and Muscoot River are classified by New
York State Department of Environmental Conservation as trout
habitat. 6 N.Y.C.R.R. § 864.6. "When excessive chlorine is
discharged to a trout stream, the trout population may decrease
since even small concentrations are lethal to fish eggs."
Bell Aff. ¶ 23. Formerly, the Muscoot River was an ideal fishing
area because of its natural beauty and abundance of trout;
however, the recent deterioration downstream of the Hallocks Brook
outlet, has rendered the Muscoot River "no longer worth a
visit." Affidavit of Robert B. Hodes, sworn to on April 24,
1996, ¶ 5.
Additionally, the metals discharged by the Defendants' Sewage
Plant, such as copper, nickel and zinc, have a severe impact on
aquatic plants and animals. For example, copper has been shown to
be toxic to young and juvenile fish. Bell Aff. ¶ 24. Defendants
admit to five violations of the copper effluent limitation since
January 1991. Burns Aff. ¶¶ 22, Ex. N. "Nickel adversely
affects the reproduction of freshwater crustaceans and fish and
nickel salts are injurious to freshwater plants." Bell Aff.
¶ 26. Since January of 1991, Defendants have failed to monitor
their effluent for nickel on two occasions. Burns Aff. ¶ 11, Ex.
F-G. The numerous impacts of zinc on freshwater plants and animals
include: (1) bioaccumulation of zinc in freshwater tissues can
reach 1,130 times the concentration of zinc in water; (2) adverse
changes in the morphology and physiology of fish; (3) cellular
breakdown of fish gills; and (4) inhibition of growth and
maturation of freshwater organisms. Bell Aff. ¶ 27. The
Defendants' have failed to monitor their effluent for zinc on two
occasions. Burns Aff. ¶ 11, Ex. F-G.
At present, the Sewage Plant is hydraulically overloaded which
decreases the plant's ability to remove pollutants. Bell Aff. ¶
12. Any additional sewer hook-ups will increase the flow to the
Sewage Plant. This additional flow will exacerbate the degradation
of Hallocks Mill Brook by increasing the release of chlorine and
metals thereby irreparably injuring the Plaintiff's members who
are unable to fish there.
2. Drinking Water Hazards.
Defendants' violations also irreparably harm Plaintiff's
members, who drink, cook, and bathe in the water from the Muscoot
and New Croton reservoirs as New York City and Westchester water
consumers, by introducing pathogens and toxic substances into
their drinking water supply. Bell Aff. ¶¶ 20-27.
Defendants have exceeded the Sewage Plant's effluent limitation
for lead on two occasions since January of 1991. Burns Aff. ¶ 22,
Ex. L-M. Lead is a toxic metal, which accumulates in the tissues
of humans and freshwater fish. Bell Aff. ¶ 25. Lead can cause
irreversible brain damage to children who ingest water or other
substances contaminated with lead. Id. ¶¶ 21, 25.
Defendants' permit violations expose water users to pathogens
as well. Defendants' fecal coliform violations indicate the
discharge of incompletely disinfected effluent and suggest the
presence of other pathogenic bacteria and viruses in the effluent.
Bell Aff. ¶ 22. According to Dr. Bell, reduced detention times
result in less efficient removal of pollutants, such as bacteria
and viruses. Bell Aff. ¶ 12. Anne Hearst, a Riverkeeper Director
and New York City resident, will not let her children drink from
the home tap because of her "fear it is contaminated by
sewage in the reservoir." Affidavit of Anne Hearst, sworn to
on April 25, 1996, ¶¶ 5-7. David Fell, another Riverkeeper
Director and New York City resident, attests that he "fear[s]
that the tap water in his home is not clean" and that he is
"forced to filter the water before [he] uses it."
Affidavit of David Fell, sworn to October 10, 1996, ¶ 5.
Even when flow volumes are within its permitted capacity, the
Sewage Plant has violated the permit limitations for CBOD,
Suspended Solids, Chlorine and other pollutants. See e.g.,
Burns Aff. ¶ 17 (from May 1995 to September 1995, no flow
violations occurred, but chlorine and suspended solids violations
persisted). Additional flows only exacerbate the violations and
increase the discharge of incompletely treated sewage into the
Hallocks Mill Brook. The Sewage Plant has a permitted monthly
average flow of 1.5 million gallons per day. See Burns Aff.
Ex. A (SPDES permit) and Bell Aff. ¶ 11. However, the Sewage
Plant has had monthly flow averages for flow as high as 2.4
million gallons per day and on some days, the Sewage Plant flows
have exceeded 6.8 million gallons. See Burns Aff. Ex. F
(March 1994 WFOR), M (July 1996 WFOR). These levels greatly exceed
the plant's capacity to treat sewage. Bell Aff. ¶ 11. Such
exceedences escalate the detrimental environmental impacts
inherent in discharging incompletely treated sewage into an
already overloaded receiving water. Every additional hook-up adds
to this risk since each hook-up will further reduce holding times.
The water users served by this system deserve not simply
drinkable water, but water that does not have a single drop of
"sewage" in it. Because existing flows already exceed
Defendants' ability to treat sewage, connection of additional
sewer hook-ups is the equivalent of running pipes from toilets
directly into a drinking water supply. For these reasons, each new
hook-up will cause irreparable harm. A moratorium on
"hook-ups" to this sewage treatment plant is therefore
essential.
B. The Plaintiff Has Established A Substantial Likelihood Of
Success On The Merits, As The Record Establishes Clear And
Admitted Violations Of The Clean Water Act.
The Defendants are chronic violators of the Clean Water Act
("CWA"). Defendants in their own WFORs admit to
violating their permit 1,226 times between January, 1991 and
April, 1995. See Burns Aff. ¶ 11, Ex. F-G. To violate a
permit condition is to violate the CWA. EPA v. California ex
rel. State Water Resources Control Bd., 426 U.S. 200, 205
(1976).
Under the CWA, "compliance is a matter of strict liability
and a defendant's intention to comply or good faith attempt to do
so does not excuse a violation." Connecticut Fund for the
Env't v. Upjohn Co., 660 F. Supp. 1397, 1409 (D. Conn. 1987)(citing
United States v. Earth Sciences, Inc., 599 F.2d 368, 374
(10th Cir. 1979)); Connecticut Fund for the Env't v. Job
Plating Co., 623 F. Supp. 207, 218 (D. Conn. 1985)(citations
omitted). The issue of liability is determined based on a
defendant's WFORs, and the undisputed facts in this case show that
permit levels are exceeded. See Coalition for a Liveable
West Side, Inc., v. New York City Department of Envtl. Protection,
830 F. Supp. 194, 198 (S.D.N.Y. 1993)(citing United
States v. CPS Chemical Co., 779 F. Supp. 437, 442 (E.D. Ark.
1991); Natural Resources Defense Council v. Loewengart &
Co., 776 F. Supp. 996, 998 (M.D. Pa. 1991)); see also
Job Plating Co., 623 F. Supp. at 218 (citations omitted).
Therefore, Riverkeeper is substantially likely to succeed on the
merits.
C. Alternatively, And At A Minimum, Plaintiff Has
Established A Sufficiently Serious Ground For Litigation And A
Balance Of Hardships Tipping Decidedly In Its Favor.
The Second Circuit has held that as an alternative to showing a
likelihood of success on the merits, the moving party is entitled
to injunction if it establishes a sufficiently serious ground for
litigation and a balance of hardships tipping decidedly in its
favor. Stickley, 79 F.3d at 261-62 (citations omitted). As
demonstrated in Point B, supra, Plaintiff has clearly
established a serious ground for litigation on the merits.
The balance of hardships also clearly favors Plaintiff. If the
Defendants are permitted even one additional hook-up, the Sewage
Plant's permit violations will worsen. As a result, the Plaintiff
will suffer the immediate, severe, and irreparable injuries as
noted in Point A, supra.
By comparison, Defendants will not suffer any significant harm
if this Court enjoins further sewer hook-ups. The issuance of a
preliminary injunction will not alter the status quo or cause
undue inconvenience or loss to the Defendants. Defendants have no
legitimate interest in expanding its population when it lacks the
infrastructure to serve its existing population in compliance with
the law. All properties presently served by the Sewage Plant will
continue to be served even if a moratorium is granted.
D. This Court Should Issue Effective Injunctive Relief To
Stop The Violations Of Federal Law.
Section 505(a) of the Act, 33 U.S.C. § 1365(a), gives district
courts jurisdiction "to enforce . . . an effluent standard or
limitation" in a suit brought by citizen plaintiffs and
specifically refers to the availability of "a temporary
restraining order or preliminary injunction" in § 505(d), 33
U.S.C. § 1365(d). Consequently, this Court's jurisdiction under
§ 505(a) plainly includes the authority to issue whatever
injunctive relief is necessary to ensure a defendant's compliance
with the Act. The D.C. Circuit has explicitly recognized that a
sewer hook-up moratorium may be necessary to enforce a sewage
treatment plant's effluent limitations. Montgomery Envtl.
Coalition v. Costle, 646 F.2d 568, 588 (D.C. Cir. 1980).
CONCLUSION
For the foregoing reasons, Plaintiff respectfully requests this
Court to issue a preliminary injunction imposing a sewer hook-up
moratorium.
Dated: October 15, 1996
White Plains, New York
Respectfully submitted,
KARL S. COPLAN - KC 3877
ROBERT F. KENNEDY, JR. - RK 5906
STEPHANIE L. BURNS, LEGAL INTERN
SEAN F. NOLON, LEGAL INTERN
Pace Environmental Litigation Clinic, Inc.
78 North Broadway
White Plains, New York 10603
(914) 422-4343; (914) 422-4437 fax
Attorneys for Plaintiff
|
|